Coweta County voters decide fate of $17 billion data center campus
Georgia Home Rule petition clears signature bar by 94 votes, ballot would ban data centers countywide as billion-dollar tax forecast shrinks to $100 million
Images
zerohedge.com
Jacqueline Lassetter, foreground, attends a Coweta County Commission meeting on December 16, 2025. (Credit: Edward Donnelly/DeSmog)
Edward Donnelly/DeSmog)
This is a rendering of Project Sail, a nine-building data center campus proposed for Coweta County. (Courtesy of Coweta County/Prologis)
Courtesy of Coweta County/Prologis
zerohedge.com
Voters in Coweta County, Georgia, will decide on January 12 whether to repeal the rezoning behind Project Sail, a $17 billion data center campus planned across more than 800 rural acres about 45 miles southwest of Atlanta. Probate Judge Carrie B. Markham ordered the special election on Monday, after the county's director of elections verified 11,065 signatures on a residents' petition — 94 more than required.
The petition was filed on October 16 under the Home Rule provision of the Georgia Constitution, which lets signatures from 10 percent of a county's electorate force a vote on a zoning decision. Against a threshold of 10,971, drawn from 109,703 active electors, organizers turned in 14,820. The ballot question does not stop at repealing the April 7 rezoning, which commissioners approved 3-2. As quoted in the court order, it would delete data centers as a permitted use from every zoning district in the county and prohibit data center campuses and cryptocurrency mining outright.
Atlas Development, the Buford-based company that filed the rezoning application, objected to the petition on October 23. Markham threw the objection out the same day she called the election, finding that under Georgia Supreme Court precedent no party has legal standing to challenge a Home Rule petition — precedent from a unanimous ruling last year in the fight over Hogg Hummock, the Gullah Geechee community on Sapelo Island, where the court held a county zoning ordinance subject to the same referendum procedure. Prologis, the San Francisco industrial REIT under contract to take over the project, said in October that the petition "does not change our commitment to Project Sail."
Atlas's filings with the Georgia Department of Community Affairs describe what that commitment contains: 13 buildings of roughly 378,000 square feet each plus substations, finished by the end of 2036 and valued at $17.16 billion at build-out, drawing 9.1 million gallons of water a day, producing 3.03 million gallons of sewage a day and 800 tons of solid waste a year. Prologis has since pitched a smaller version — nine buildings totaling about 4.3 million square feet, drawing roughly 900 megawatts. Atlas first projected the campus would generate more than $1 billion a year in local taxes; the Atlanta Journal-Constitution found that figure erroneous, and Prologis's latest projection is about $100 million.
A week earlier, the council of Aurora, Colorado halted new data centers across much of that city, hours after Vantage Data Centers abandoned its planned Trident megaproject there and promised to remain a responsible partner while scouting a new site. In April, Prologis executive JC Witt said the Coweta site was chosen partly for its proximity to Georgia Power's Plant Yates, and that "the question isn't if this site will be developed. It's just how." The how now runs through a ballot measure that would bar the industry from the county entirely.
The county will pay for the election and run it on its normal precincts, with the result certified in court. Its communications manager, Cathy Wickey, said the county "became aware of this news at the same time as our citizens" and is still assessing the implications.